Road Closures on Minton Road Between Jupiter Blvd and Malabar Rd: What You Need to Know
Major Paving Project to Cause Full Road Closure from July 8 to July 30
Interactive edition of this story
PALM BAY, FL β Residents of Palm Bay should prepare for significant road closures as the city embarks on a major paving project on Minton Road. The contractor, Ranger Construction, will be performing extensive road work that necessitates a full closure of Minton Road between Jupiter Blvd and Malabar Rd from July 8, 2024, to July 30, 2024. Hereβs what you need to know to navigate this period smoothly.
Road Closure Details
Location and Duration:
Minton Road: Between Jupiter Blvd and Malabar Rd
Closure Dates: July 8, 2024, to July 30, 2024
Closure Times: 24 hours a day
Detours and Traffic Adjustments:
Full Closure: Minton Rd between Malabar and Jupiter
Westbound Malabar to Southbound Minton: Turn lane closure
Southbound Minton Approaching Malabar: Outside lane closure transitioning to a through lane closure at the traffic light
Eastbound Jupiter to Northbound Minton: Turn lane closure
Safety and Coordination
Ranger Construction has placed Changeable Message Signs (CMS) and channelizing devices to guide traffic and ensure safety. Motorists are advised to use caution in these areas and follow the posted detour routes.
Contact Information:
For any questions regarding these lane and road closures, please contact Public Works customer service at (321) 952-3438.
Project Overview
This road closure is part of a larger paving project aimed at improving the infrastructure of Minton Road and Waco Blvd. The project will utilize Full Depth Reclamation (FDR), a sustainable method that recycles existing pavement materials to create a stronger, more durable road base.
Key Details:
Minton Road: FDR to a depth of 12 inches
Waco Blvd: FDR to a depth of 8 inches
Paving: New asphalt layer for a smooth driving surface
Previous Coverage
For more detailed information on the projectβs background and the bidding process, you can refer to our previous articles:
Smooth Sailing Ahead: The Comprehensive Guide to Palm Bayβs Road Improvements
Minton Rd and Waco Blvd Paving Project: What You Need to Know
Benefits of Full Depth Reclamation
FDR is not just about resurfacing the road; it enhances the structural integrity of the roadway, leading to longer-lasting results. This environmentally friendly process reuses existing materials, reducing waste and the need for new raw materials.
Community Coordination
The contractor will coordinate closely with Columbia Elementary School and local residents to ensure minimal disruption. Residents will be informed well in advance of any changes or updates to the construction schedule.
Staying Informed
The Palm Bayer is committed to keeping the community informed with real-time updates on the Minton Road and Waco Blvd paving project. Stay tuned for the latest news and information to navigate these changes smoothly.π΄π§